| News

Update: Complete closure of Highway 20 east ramp to Des Sources Boulevard northbound

Update: October 10, 2023

Over the next few days and into early December, MTQ work will result in the complete closure of Exit 53 from Highway 20 eastbound to Des Sources Boulevard northbound. The work will also result in the closure of the small section between the Westbound offramp and the Westbound onramp of highway 20 at Des Sources Boulevard. Motorists will have access to a detour via the Dorval roundabout, as well as through Avenue Cardinale and Avenue Donegani.

These phase changes will allow the reopening of exit 53 from autoroute 20 west to Des Sources Boulevard.

Thank you for your understanding,

Information: Ministère des Transports, 511.

Website: transports.gouv.qc.ca

From October 1 to 30, night closure of Donegani Avenue

August 31, 2023

The City of Pointe-Claire wishes to inform you that, due to work being carried out by the MTQ on Des Sources Interchange, Donegani Avenue will remain completely closed from September 1 to 30, between 10:30 p.m. and 5 a.m. This closure will be between Des Sources Boulevard and Chester Avenue.

Thank you for your understanding,

Reopening of exit 53 of the Des Sources interchange postponed

August 29, 2023

The City of Pointe-Claire would like to inform you that the work carried out by the MTQ at exit 53 on Highway 20 westbound at Des Sources Boulevard will be extended past the expected end date of August 30, 2023.

Road users will be redirected towards a detour to exit 50-N northbound on Saint-Jean Boulevard.

Thank you for your understanding.

Closures – Work on the Des Sources interchange

June 23, 2023

From June 25 to August 30, 2023, the work carried out by the MTQ will result in the complete closure of Exit 53 leading from Highway 20 westbound to Des Sources Boulevard northbound. Motorists will be offered a detour through Exit 50-N, northbound towards boulevard Saint-Jean.

Thank you for your understanding,

Update: May 26, 2023

From May 26 to June 16, night work by the MTQ will require the complete closure of Donegani Avenue, between des Sources Boulevard and Chester Avenue, and an obstruction of the right lane of des Sources Boulevard southbound, from 10:30 p.m. to 5 a.m.

In addition, from May 26 to 29, work will force the complete closure of exit 53 leading from Highway 20 westbound to des Sources Boulevard. Motorists will be able to take a detour to exit 50-N towards Saint-Jean Boulevard northbound.

Update: May 19, 2023

From May 22 to June 16, MTQ work will require the obstruction of Donegani Avenue, between Des Sources Boulevard and Chester Avenue, alternating between the westbound and eastbound lanes. Flaggers will be present to direct traffic.

Update: May 9, 2023

MTQ work on Des Sources Interchange will result in an obstruction eastbound on de l’Église Avenue, near Des Sources Boulevard, from May 10 to 12, between 7 a.m. and 5 p.m.

Thank you for your understanding.

Closures: Preparatory work on the Des Sources interchange

May 5, 2023

The City of Pointe-Claire wishes to inform you that the Ministère des Transports du Québec (MTQ) will proceed with repair work on the Des Sources Boulevard interchange of Highway 20. During the month of May, obstructions and closures will occur in the preparatory phase of the repair of the Des Sources interchange structures.

From May 7 to 12, the MTQ’s work will cause a partial closure of the left lane of Des Sources Boulevard northbound, and an obstruction of the roundabout’s shoulder.

Also, from May 7 to 12, Donegani Avenue will be completely closed for night work, this work will be completed between Des Sources Boulevard and Chester Avenue, from 10:30 p.m. to 5 a.m.

Work will lead to the complete closure of the northbound ramp of Exit 53 of the Des Sources interchange in progress over the following weekends:

  • The weekend of May 6 & 7;
  • The weekend of May 12 & 15;
  • On the weekend of May 27 & 28, one lane will be maintained on Des Sources Boulevard northbound;
  • On the weekend of June 2 & 5, depending on the progress, the northbound ramp of Des Sources Boulevard, near Highway 20 westbound, may be closed;
  • On the weekend of June 10 & 11, depending on the progress, the northbound ramp of Des Sources Boulevard, near Highway 20 eastbound, may be closed;

After the preparatory work, the repair work will lead to various complete closures up to November 2023. Communications with all the details for this work will follow.

Thank you for your understanding.

Information: Ministère des Transports, 511

Website : transports.gouv.qc.ca