Replacement of streetlights on the North service road of the Félix-Leclerc Highway (40) as well as on the Sources Nord Boulevard
Description
Places: North service road of the Félix-Leclerc Highway (40) and the ramp, between Bancroft Avenue and Des Sources Boulevard, as well as on Sources Nord Boulevard, between the ramp and the viaduct.
Timeline
August 2025
Conversion of the power supply to 240V
Installation of new streetlights with LED fixtures
October 2025
End of work.