Improvement Work on Du Bord-du-Lac–Lakeshore Road, between Lakeview and Fifth Avenues
The City of Pointe-Claire informs you that road improvement work will take place on Du Bord-du-Lac–Lakeshore Road, between Lakeview Avenue and Fifth Avenue.
Work will begin during the week of August 3 and continue through the end of October 2026.
The project will be carried out in six phases. Before the start of each phase, communications will be issued to inform you about the upcoming work.
Phase 1: August 3 to September 9, 2026
This first phase will include the following work:
- pulverizing the road surface;
- rebuilding and repairing certain manholes and sumps;
- rebuilding sidewalks and curbs;
- levelling the foundation and laying the base course.
Traffic
During this phase, Du Bord-du-Lac–Lakeshore Road will be closed between Fifth Avenue and Lakeview Avenue. Only local traffic will be permitted.
During sidewalk reconstruction, access to driveways may be limited at certain times.
During the work, motorists and pedestrians will be required to use the detour via Lakeview Avenue and Fifth Avenue.
Overnight parking will be permitted on the surrounding streets. We ask that you follow the temporary signage in place.
For more information on this project or to learn about the next phases, visit the web page Resurfacing Du Bord-du-Lac–Lakeshore Road, from Entrance of Highway 20 to Lakeside Avenue.
We appreciate your understanding and cooperation.