Continuation of the works: Lakeside Avenue and Bord-du-Lac–Lakeshore Road

Work carried out by the City of Montreal

Description

Intersection of the work: Lakeside Avenue, between Highway 20 and Bord-du-Lac-Lakeshore Road, and Bord-du-Lac-Lakeshore Road, between Ovide Avenue and Lakeside Avenue.

To know the work sequences, consult the work notice of the City of Montreal. 

Timeline

October - December 2023

Installation of a 900 mm pipe;
Construction of a valve chamber;
Replacement of catch basins;
Connection of citizens' storm service entries;
Repair of the roadway and sidewalks;
Lining of the existing 1200 mm pipe.

Summer 2024

Construction and replacement of sewer pipes;
Reconstruction of sidewalks and roadways;
Service connections and earthwork.

April 2025

Finalization of pipeline construction work.

Mid-June 2025

End of works.