Major construction sites in 2023

Again this year, the City is maintaining significant investment in the reconstruction and maintenance of municipal infrastructure to ensure that roads, sidewalks and public utility services are in good condition for the next 50 years.
Pre-project home inspection form to permit service reconstruction work  

Please complete the form and return it before the date indicated in the letter, by e-mail to ingenierie@pointe-claire.ca, in person to Pointe-Claire City Hall, or by mail to:

Engineering and Buildings Department
451 Saint-Jean Boulevard
Pointe-Claire, Québec H9R 3J3

Tony-Proudfoot Park: Construction of an accessible sanitary station

At Tony-Proudfoot Park
From May to June 2023

  • Addition of a universally accessible sanitary station with an adapted changing table and a water fountain
  • Set up of a storage room
  • Installation of an electrical panel in the building

Northview Park: Renovation of the baseball field

At Northview Park
From May to September 2023

  • Upgrading and securing of the baseball field
  • Installation of a backstop, fences and benches for the players
  • Covering of the clay surface
  • Excavation, drainage, replacement of equipment
  • Concrete works and repairs to grass surfaces

Repairs to pedestrian trails at various locations on the territory

Trails between avenues Lucerne and Montrose
Trail between avenues Montrose and Elmwood
Trail between avenues Elgin and Jefferson
Trail in Grande-Anse Park
From April to May 2023

  • Reconstruction of asphalt trails
  • Repair of grass surfaces

Bayview Park and reading garden: Planting

At Bayview Park and in the reading garden in Sara’s Enchanted Forest
From May to June 2023

  • Revegetation of Bayview Park by creating a flowerbed and planting shrubs
  • Revegetation of the reading garden in Sara’s Enchanted Forest, near the Central Library

Between avenues Bancroft and Tecumseh: Structural rehabilitation of the drinking water pipe

Westbound service road of the Félix-Leclerc highway (40) between avenues Bancroft and Tecumseh
From April to July 2023

  • Installation of a temporary drinking water supply network
  • Replacement of drinking water service connections
  • Structural rehabilitation (cladding) of a water main

Des Sources Boulevard: Structural rehabilitation of the drinking water pipe

Des Sources Boulevard between avenues Chanteclerc and Cornish
From April to June 2023

  • Installation of a temporary drinking water supply network
  • Replacement of drinking water service connections
  • Structural rehabilitation (cladding) of a water main

Walton sector: Development of a green space

Walton sector
From May to June 2023

  • Extension of the existing trail to Braebrook Avenue
  • Addition of fences to delimit the green space
  • Laying of grass on the green space
  • Planting of plants

Belmont and Clearpoint parks: Lighting work on the pedestrian path and sports field

At Belmont and Clearpoint parks
From September to October 2023

  • Construction of a new solar lighting system on the pedestrian path at Belmont Park
  • Modifications to the existing lighting system on the tennis court at Clearpoint Park

Edgewater Park: Redevelopment of the grounds

Edgewater Park
From August to September 2023

  • Addition of two picnic tables accessible to people with reduced mobility
  • Creation of an accessible gravel trail

Tudor Avenue: Structural rehabilitation of the drinking water pipe

Tudor Avenue between avenues Chanteclerc and Cornish
From June to August 2023

  • Installation of a temporary drinking water supply network
  • Replacement of drinking water service connections
  • Structural rehabilitation (cladding) of a water main

Lakeview Avenue and Bord-du-Lac – Lakeshore Road: Partial reconstruction

Work done in collaboration with Ville de Montréal
Lakeside Avenue, between Highway 20 and Bord-du-Lac – Lakeshore Road (to be completed in 2023)
Lakeview Avenue, between Bord-du-Lac – Lakeshore Road and Saint-Jean Boulevard (to be completed in 2024)
Bord-du-Lac – Lakeshore Road (between avenues Lakeside and Lakeview (to be completed in 2024)
From October to December 2023, and in 2024

  • Construction and replacement of sewer lines
  • Reconstruction of sidewalks and roadways
  • Service connections and excavation

Des Sources interchange: Repair of structures

Work carried out by the Ministère des Transports du Québec (MTQ)
From May to November 2023, and in 2024

  • Repair of the Des Sources interchange structures over Highway 20 (2023)
  • Repair to the pedestrian overpass (2024)

General information

General information for all construction sites

Certificate of authorization - Planning Department

To widen your driveway or replace the service connections (from the house to the property line) you must submit your request to the Planning Department.

Processing time for a full application: 30 days

Information on permits

urbanisme@pointe-claire.ca

514-630-1206

Collections

For the collections, leave your bins, bags of leaves, bulky and mattresses, sofas and armchairs at the end of your driveway before 7 a.m. the day of the collection. The contractor is responsible for moving them in order for your waste to be collected.

Claims

A  claim must be sent within 15 days to the Legal Affaires and City Clerk’s office. You may take date stamped pictures of the interior and exterior of your residence before the start of the construction.

Information on claims

Residents with reduced mobility

If you or another resident in the work zone has limited mobility or any other issue that may be impacted by the work, please contact the Engineering Department at 514-630-1208 or at ingenierie@pointe-claire.ca.

We will work with the contractor in assisting the individuals affected.

Moving

If you are planning a move, we ask that you please contact the Engineering Department at 514-630-1208 or at ingenierie@pointe-claire.ca as soon possible so that we can coordinate a schedule that works for everyone.

Watering the grass

The contractor will lay sod in the areas indicated by the site supervisor. The City holds a guarantee for all the work carried out by the contractor. Maintenance  of the new lawn is the responsibility of the residents.